Project on Improvement and Upgrade of Highway No. 10

Project Title: Project on improvement and upgrade of National Highway No. 10 (km 92 + 900 - km 98 + 400) from La Uyen bridge to Tan De bridge
Owner: TASCO JCS
Construction site: Thai Binh Province
Total investment: 311,203 billion VND (excluding the cost of site clearance)
Scope of the project:

  • Total length: 5.5 km;
  • Type, class of works: class I highway bridge traffic work;
  • Width of road bed is 24m. Of which:
  • Design speed:100km / h;

Form of investment:

The Investment is made in the Build – Operate - Transfer form (BOT contract). The toll collected at Tan De bridge toll station will be used to return the capital for the project, and the time of collection is expected to be 21.33 years.


Project duration:

24 months

PROJECT ON IMPROVEMENT AND UPGRADE OF NATIONAL HIGHWAY NO. 10
SECTION FROM LA UYEN BRIDGE TO TAN DE BRIDGE

Project Title: Project on improvement and upgrade of National Highway No. 10 (km 92 + 900 - km 98 + 400) from La Uyen bridge to Tan De bridge
Owner: TASCO JCS
Construction site: Thai Binh Province
Total investment: 311,203 billion VND (excluding the cost of site clearance)
Scope of the project:

  • Total length: 5.5 km;
  • Type, class of works: class I highway bridge traffic work;
  • Width of road bed is 24m. Of which:
    - Motor vehicle lane: 4x3.75 = 15.0m
    - Non-motorized vehicle lane: 2x2.50 = 5.0m
    - Median strip: 1x1.50 = 1.50m
    - Central safety lane: 2x0.50 = 1.0m
    - Left margin: = 0.5m
    - Right margin: = 1.0m
  • Design speed:100km / h;
  • Works located on the road route include:
  • - Drainage culverts across the road
    - Vertical trench made of reinforced concrete
    - Bridges on the road route: La Uyen bridge, Thuong Dien bridge, Nhi bridge, Nhat bridge, Tu Tan bridge, La Dien bridge.

Form of investment: The Investment is made in the Build – Operate - Transfer form (BOT contract). The toll collected at Tan De bridge toll station will be used to return the capital for the project, and the time of collection is expected to be 21.33 years.
Project duration: 24 months

  • Estimated commencement time: September 2008
  • Expected completion time: September 2010

[video(3924)]

Legal bases:

  • The Ministry of Transport issued Decision No. 4153/QD-BGTVT on December 28th, 2007 on approving the project proposal on improvement and upgrade of National Highway No. 10 (Km92+900 to Km98+400) from Tan De bridge to La Uyen bridge under local BOT form;
  • Vietnam Roads Bureau issued Document No. 14783/CDBVN-TD on April 23rd, 2008 on evaluating the basic design of the project;
  • TASCO JSC made Decision No. 98/QD-TASCO on June 20th, 2008 on approving the project on improvement and upgrade of National Highway No. 10 (km 92 + 900 - km 98 + 400) from La Uyen bridge to Tan De bridge under BOT form;
  • The project was officially signed between Vietnam Roads Bureau and Tasco Joint Stock Company on June 24th, 2008 under Contract No. 28/HD.BOT-CDBVN.
Project on Improvement and Upgrade of Highway No. 10 ảnh 1

Tin cùng chuyên mục

Thủ tướng Chính phủ Phạm Minh Chính dự, chứng kiến Lễ ký, trao 26 thỏa thuận hợp tác của các bộ, ngành và doanh nghiệp Việt Nam và đối tác Anh.

Thủ tướng Phạm Minh Chính dự Hội nghị COP26 và làm việc tại Anh: Ký kết thỏa thuận hợp tác trị giá hàng tỷ USD

(PLVN) - Nhân chuyến tham dự Hội nghị COP26 và làm việc tại Vương quốc Anh, chiều 31/10 (giờ địa phương), tại thành phố Edinburg, Scotland, Thủ tướng Chính phủ Phạm Minh Chính đã dự, chứng kiến lễ ký, trao 26 thỏa thuận hợp tác trong các lĩnh vực thương mại, nông nghiệp, năng lượng, y tế, giáo dục, đào tạo, bảo vệ môi trường, thể thao... của các bộ, ngành và doanh nghiệp Việt Nam và đối tác Anh.

Đọc thêm

Giảm tải mật độ, hạn chế lây nhiễm trong khu cách ly

làm thủ tục tiếp nhận công dân vào khu cách ly tại Trường Quân sự Bộ Tư lệnh Thủ đô. Ảnh: báo Lao động (chụp tháng 2/2020)
(PLVN) - Những ngày vừa qua, số ca F1 chuyển biến thành F0 tăng nhanh nên TP Hà Nội đã chỉ đạo xét nghiệm toàn bộ số F1 đang cách ly để sàng lọc, rà soát mà không cần chờ đủ thời gian 7 ngày theo quy định. Qua xét nghiệm đã xác định thêm 27 ca bệnh chuyển từ F1 thành F0.

Những nữ Công an tỉnh Phú Thọ nhiệt huyết trong công việc

Chiến sỹ Cảnh sát nhập dữ liệu thông tin của người dân.
(PLVN) - Trong bất kể lĩnh vực công tác nào, thì những “bông hồng thép”- nữ cán bộ, chiến sĩ Phòng Cảnh sát quản lý hành chính về trật tự xã hội Công an Phú Thọ đều luôn nỗ lực phấn đấu hoàn thành tốt nhiệm vụ, góp phần mang lại cuộc sống bình yên, hạnh phúc cho nhân dân.