Phu Van Bridge Project

Phu Van Bridge crosses Nhue river and it is located in the area of Phu Ly town.  This location is within the plan of upgrading infrastructure for natural disaster prevention in the flood control zone of Day river in Ha Nam province and the plan on transport development in Ha Nam province in the period 2003-2010, and orientation towards 2020. The old bridge was built a long time ago and it is narrow, small, and made of steel beam; its concrete deck has been degraded so it does not meet current traffic needs.

PHU VAN BRIDGE PROJECT – PHU LY TOWN – HA NAM PROVINCE

Phu Van Bridge crosses Nhue river and it is located in the area of Phu Ly town.  This location is within the plan of upgrading infrastructure for natural disaster prevention in the flood control zone of Day river in Ha Nam province and the plan on transport development in Ha Nam province in the period 2003-2010, and orientation towards 2020. The old bridge was built a long time ago and it is narrow, small, and made of steel beam; its concrete deck has been degraded so it does not meet current traffic needs.

Phu Van Bridge Project ảnh 1

Phu Van Bridge Project ảnh 2

The newly built bridge is about 350m from Nhue river and Chau Giang river towards the upstream of Nhue river. The total length of the project is 1367.96m with the following main technical parameters:

Phu Van Bridge Project ảnh 3

Bridge section:

  • Scope: bridge is built to be permanent
  • Design load: HL-93, pedestrian section 3 kN/m2 under procedure 22TCN272-05
  • Bridge width: K = 15.0m, total width B = 16.0m
  • Simple span bridge with super-T pre-stressed and pre-cast beam
  • Span diagram (39 +4 x40 +39) m
  • Upper structure: cross-section is 16m wide, including 07 super-T beam slabs; distance between beams is 2.22m; beam-height is 1.75m. Bridge deck is made of reinforced concrete poured in place with thickness ranging from 15-22cm.
  • Lower structure: Bridge support is made of reinforced concrete poured in place on bored pile foundation with a diameter of 1.5m
  • Navigational clearance - river level V: B = 25m, H = 3.5m.
  • Seismological level: Level 8 under Standard 22TCN 272-05
  • Total length of the bridge calculated up to 02 parapet walls is 248.9m.

02 bridge-end way:

  • Local way has its 80-speed level under Standard 20TCN 104-83 according to TCVN 4054-98.
  • Road bed width: Bbed= 42m 2 ÷ 4 including 2 ÷ 4 motor vehicle lanes with width of 3.75 m per lane; 02 non-motorized vehicle lanes with width of 2.50m per lane; sidewalks have 6.00m wide per side and median strip is 9.00m wide.
  • Road surface designed with high-level A1 Eyc= 1600 daN/cm2
  • Minimum curve radius: Rmin = 250m.
  • Minimum convex vertical curve radius: Rmin = 4,000m.
  • Minimum sag vertical curve radius: Rmin = 1,500m
  • Maximum longitudinal slope IMAX = 6%
  • Surface cross slope 2%; pavement -1.5%
  • Axial design load: 12 tons.

Barrier wall:

  • Bridge-end way is closed to abutment; 02 sides are arranged with shaped U and L reinforced concrete walls on reinforced concrete pile foundations of 30x30cm, 40x40cm and shallow foundation
  • In National highway 1A: wall length L = 116.86m, on reinforced concrete foundation 30x30cm, pile length L = 13-18m
  • In Phu Van commune: wall length L = 144.36m, on reinforced concrete pile foundation 40x40cm; average pile length L = 30-46m and shallow foundation
  • Outside barrier wall is decorated with decorative patterns to increase aesthetics.

After Phu Van Bridge is completed, it will be extremely important to make a main arterial road to connect Phu Ly Town to Phu Van commune in the northwest of the town, creating a transport road to build other infrastructures in the local area in accordance with the approved plan.

Tin cùng chuyên mục

Thủ tướng Chính phủ Phạm Minh Chính dự, chứng kiến Lễ ký, trao 26 thỏa thuận hợp tác của các bộ, ngành và doanh nghiệp Việt Nam và đối tác Anh.

Thủ tướng Phạm Minh Chính dự Hội nghị COP26 và làm việc tại Anh: Ký kết thỏa thuận hợp tác trị giá hàng tỷ USD

(PLVN) - Nhân chuyến tham dự Hội nghị COP26 và làm việc tại Vương quốc Anh, chiều 31/10 (giờ địa phương), tại thành phố Edinburg, Scotland, Thủ tướng Chính phủ Phạm Minh Chính đã dự, chứng kiến lễ ký, trao 26 thỏa thuận hợp tác trong các lĩnh vực thương mại, nông nghiệp, năng lượng, y tế, giáo dục, đào tạo, bảo vệ môi trường, thể thao... của các bộ, ngành và doanh nghiệp Việt Nam và đối tác Anh.

Đọc thêm

Giảm tải mật độ, hạn chế lây nhiễm trong khu cách ly

làm thủ tục tiếp nhận công dân vào khu cách ly tại Trường Quân sự Bộ Tư lệnh Thủ đô. Ảnh: báo Lao động (chụp tháng 2/2020)
(PLVN) - Những ngày vừa qua, số ca F1 chuyển biến thành F0 tăng nhanh nên TP Hà Nội đã chỉ đạo xét nghiệm toàn bộ số F1 đang cách ly để sàng lọc, rà soát mà không cần chờ đủ thời gian 7 ngày theo quy định. Qua xét nghiệm đã xác định thêm 27 ca bệnh chuyển từ F1 thành F0.

Những nữ Công an tỉnh Phú Thọ nhiệt huyết trong công việc

Chiến sỹ Cảnh sát nhập dữ liệu thông tin của người dân.
(PLVN) - Trong bất kể lĩnh vực công tác nào, thì những “bông hồng thép”- nữ cán bộ, chiến sĩ Phòng Cảnh sát quản lý hành chính về trật tự xã hội Công an Phú Thọ đều luôn nỗ lực phấn đấu hoàn thành tốt nhiệm vụ, góp phần mang lại cuộc sống bình yên, hạnh phúc cho nhân dân.